Once all required project activation items have been completed and submitted, OCI’s Program Manager, listed in the program guidelines, will be able activate the project.
The activation date of the project will determine the start date and the duration stated in the application will determine the project end date (e.g., if the activation date is January 30, 2018 and the project duration is nine months, the project end date will be October 30, 2018).
These dates are automatically generated and will not be changed. If additional time is required to complete the project milestones, please send a project extension request to your OCI Business Development Manager.